Some construction sites in Weifang were notified that bare soil coverage was not in place.
In recent days, in accordance with the relevant deployment requirements of Weifang Municipal Party Committee and Municipal Government, the party group of the Municipal Housing and Construction Bureau held a meeting to implement it, and set up three inspection teams to conduct on-site inspections at construction sites in various districts. After inspection, it was found that the bare soil coverage of some construction sites was not in place and the local earthwork coverage was not strict, so it was notified and rectified within a time limit.
On the night of April 20th, the inspection team of the Municipal Housing and Construction Bureau conducted on-site inspections on 11 construction sites and 3 municipal sites in Kuiwen District, High-tech Zone and Hanting District respectively. After inspection, it was found that the bare soil coverage of some construction sites was not in place and the local earthwork coverage was not strict.The relevant information is hereby notified as follows:
Project name: Central Royal Garden Phase II, Kuiwen District
Owner: Weifang Wen Liang Jiahao Real Estate Co., Ltd.
Construction unit: Qingdao Bohai Construction Group Co., Ltd.
Supervision unit: Shandong Qingang Engineering Construction Supervision Co., Ltd.
Existing problems: (1) The bare soil coverage of the construction site is not in place; (2) The road is muddy and not washed.
1. Project name: Huixiang Road Project
Construction unit: Housing and Urban-Rural Development Bureau of Hanting District, Weifang City
Construction unit: Weifang Changda Construction Group Co., Ltd.
Supervisor: Shandong Changlong Construction Consulting Co., Ltd.
Existing problems: local earthwork coverage is not strict.
2. Project name: Meiyuan Street (Weixian Middle Road-Zhiyuan Road, Huixian Road-Yonghui Road)
Construction unit: Housing and Urban-Rural Development Bureau of Weifang High-tech Zone
Construction unit: Weifang Changda Construction Group Co., Ltd.
Supervision unit: Weifang Engineering Construction Supervision Co., Ltd.
Existing problems: (1) The bare soil coverage of the construction site is not in place; (2) No cleaning staff was arranged to clean the car body, and there was mud on the road.
All districts and municipal development zones are requested to promptly rectify and implement in accordance with the principle of territorial management, and the rectification shall be reported to the Municipal Housing and Construction Bureau within 3 days. If there are still problems such as inadequate rectification within the time limit, relevant enterprises and responsible persons shall be given administrative punishment according to laws and regulations.
Contact: Du Guangyue; Tel: 15949752337;
Email: wfszfcxjsjzlaqk@wf.shandong.cn.
Weifang housing and urban construction bureau
April 21, 2020
On April 21st, the inspection team of the Municipal Housing and Construction Bureau conducted on-site inspections on 43 construction sites, 2 municipal sites and 3 demolition sites in Kuiwen District, High-tech Zone and Hanting District respectively. After inspection, it was found that some construction sites did not have public signs for prevention and control of dust pollution, the construction roads were not fully hardened and covered, the hardened roads were seriously dusty, wet operation was not adopted, the coverage of construction waste was not in place, the coverage of bare soil was not in place, and the coverage of dust-prone materials was not in place.The relevant information is hereby notified as follows:
1. Project name: Chunjing Garden in High-tech Zone
Construction unit: Shandong Dingtai Real Estate Development Co., Ltd., Weifang High-tech Industrial Development Zone Qingchi Street Dongligu Community Residents Committee.
Construction unit: Weifang Institute of Technology Construction and Installation Company
Supervision unit: Weifang Tianpeng Construction Supervision Co., Ltd.
Existing problems: (1) There is no public notice board for dust pollution prevention on site; (2) Construction waste coverage is not in place; (3) The area of hardened road is seriously dusty.
2. Project Name: 1# Residential Building in East Zone of Wanghou Jiayuan, High-tech Zone
Construction unit: Wangjiahoumeng Community Resident Committee of Qingchi Street Office in High-tech Zone
Construction unit: Weifang Thai Construction Co., Ltd.
Supervision unit: Weifang Tianyuan Engineering Construction Supervision Co., Ltd.
There are some problems: (1) the cleaning of the accumulated dust in the field is not in place; (2) The mixing machine is not protected against dust.
3. Project Name: Yuyuan Project in Kuiwen District
Construction unit: Weifang Chongwen Real Estate Co., Ltd.
Construction unit: Weifang Changda Construction Group Co., Ltd.
Supervisor: Weifang Blueprint Project Management Co., Ltd.
The existing problems are: (1) the building materials in the construction site are piled up in disorder; (2) The protective net coverage is not in place.
4. Project name: No.6 Xiafei, Hanting District
Construction unit: Weifang Jiarun Real Estate Co., Ltd.
Construction unit: gaomi city Guang ‘an No.1 Construction Engineering Co., Ltd.
Supervision unit: Weifang Tianpeng Construction Supervision Co., Ltd.
Problems: During the construction of supporting facilities, the exposed earthwork of the site was not covered.
1. Project name: Fudong Road, High-tech Zone (Jiankang Street-Yuqing Street)
Construction unit: Housing and Construction Bureau of Weifang High-tech Zone
Construction unit: Weihao Construction Group Co., Ltd.
Supervisor: Weifang Blueprint Project Management Co., Ltd.
There are some problems: (1) the coverage of dust-prone materials is not in place; (2) The bare soil coverage in the field is not in place.
2. Project name: Xinchang 1st Road (Yuqing Street-Xinchang Street) under Qingyin Expressway in High-tech Zone.
Construction unit: Housing and Construction Bureau of Weifang High-tech Zone
Construction unit: Shandong Rongchang Road and Bridge Engineering Co., Ltd.
Supervision unit: Shandong Weida Engineering Project Management Co., Ltd.
There are some problems: (1) Partial bare soil coverage is not in place; (2) Sprinkling dust is not in place.
1. Project Name: Demolition Project of Wolong Street South-Wenhua Road East Area in Kuiwen District
Responsible unit: Kuiwen District Collection Office
Existing problems: (1) The construction waste of the demolition site is not covered; (2) No dust suppression measures have been taken.
2. Project name: Wangjia Demolition Area, Ershilipu, Kuiwen District
Responsible unit: Ershilipu Street, Kuiwen District
Existing problems: (1) The construction waste at the demolition site is not covered; (2) No dust suppression measures have been taken.
3. Project name: Jianzhuang Village, Xisi, Kaiyuan Street Office, Hanting District
Responsible unit: Kaiyuan Street Office, Hanting District
Existing problems: (1) The earthwork at the demolition site is bare and the dust is heavy.
Fourth, bare land
Venue: Open space west of Chanhe River and south of Fuqing Street, High-tech Zone.
Existing problems: garbage and bare soil piles are not covered in place.
All districts and municipal development zones are requested to promptly rectify and implement in accordance with the principle of territorial management, and the rectification shall be reported to the Municipal Housing and Construction Bureau within 3 days. If there are still problems such as inadequate rectification within the time limit, relevant enterprises and responsible persons shall be given administrative punishment according to laws and regulations.
Contact: Du Guangyue; Tel: 15949752337;
Email: wfszfcxjsjzlaqk@wf.shandong.cn.
Weifang housing and urban construction bureau
April 22, 2020